Through both on-site visits and the review of essential documentation
Velocity confirmed that the General Contractor was building the
project in accordance with the Construction Documents, both as to
completeness and to the quality of work and materials. Velocity's
next step was to make monthly site visits to review the progress
at the job site in order to ascertain the following items:
Construction Budget Review- to ensure that funds
required are in line with percentages of work completed and that
there are sufficient funds remaining in the budget to complete the
project.
Monthly Pay Request Review - to verify that each
invoice is legitimate and correct with the proper retainage, and
ultimately make recommendations or issue approval of the disbursement
of funds.
|